Pelješac Bridge - Pelješki Most - Construction Update October 2021!

Pelješac Bridge gets its first layer of asphalt. The first 4 cm layer of asphalt is being applied to the structure of the bridge. So far 2/3 of the mainland - Pelješac road lane has been applied. The completion of the tarmacking is expected by the end of November. Also you can notice that the blue scaffolding on the bridge towers is removed. The bridge will be a multi-span cable-stayed bridge with a total length of 2,404-metre. It will comprise 13 spans, while seven will be cable-stayed - five central 285-metre spans and two outer spans. Two pylons around the 200-metre x 55-metre navigation channel will be 98-metre above sea level and 222-metre above the seabed. Build by the China Road and Bridge Corporation. INSTAGRAM: PATREON: FACEBOOK: TWITTER: FLICKR: @N02